The builder has delayed possession. How do I file a RERA complaint and what will I get?
File a complaint under Section 31 on the Delhi RERA portal against the promoter of a registered project. Under Section 18 you may withdraw and receive a refund with interest at the prescribed rate, or continue and receive interest for every month of delay until possession; compensation is claimed separately before the Adjudicating Officer.
The consumer commission is an alternative forum and the two are not mutually exclusive, but pick one. Possession without an occupancy certificate is not lawful possession. Check the project's registration number on rera.delhi.gov.in before booking; projects above 500 square metres or eight units must be registered.
What to do, in order
- Check the project's registration number on rera.delhi.gov.in; the complaint lies against the promoter of a registered project.
- Decide under Section 18 whether to withdraw and take a refund with interest, or continue and take interest for every month of delay until possession.
- File the complaint under Section 31 on the Delhi RERA portal.
- Claim compensation separately before the Adjudicating Officer.
- Pick one forum, RERA or the consumer commission, and do not treat possession without an occupancy certificate as lawful possession.
The law
Law: Sections 3, 11(4), 18, 19, 31 and 71, Real Estate (Regulation and Development) Act, 2016. Full essay: Stacked against the buyer. Read more: RERA and builder-buyer disputes.
Last reviewed: 17/10/2026
Practice area: Property and Real Estate
This page is an educational summary of the law as at 17/10/2026. It is not legal advice.