Limitation under the Delhi Municipal Corporation Act, 1957

This page sets out one proceeding under the Delhi Municipal Corporation Act, 1957: the provision, the period and the event that starts it, why the law fixes it, how to count it, whether delay can be condoned, a worked example and common mistakes.

Appeal against orders or notices on building and planned development, including sealing of unauthorised construction (Section 345A), stoppage of work (Section 344), sanction or refusal of building plans (Section 336) and cancellation of sanction (Section 338) (Section 347B): what is the time limit?

Provision
Section 347B(2) and proviso
Forum
Appellate Tribunal, Municipal Corporation of Delhi (ATMCD)
Period
30 days
In the words of the entry
Thirty days from the date of the order or notice appealed against
The clock starts
The date of the order or notice (not the date of its receipt)

Steps in order

  1. Further appeal against the ATMCD order: 30 days from the date of the Appellate Tribunal's order, to the Administrator (Section 347D(1) and (2), applying Section 347B(2)).

Why the law fixes this period

Building and sealing orders concern public safety and planned development, so challenges must be brought quickly before the position on the ground changes. The Tribunal may still hear a late appeal where the delay is explained.

How to calculate

Condonation of delay

Can delay be condoned?
Yes
Provision
Proviso to Section 347B(2)
Test
sufficient cause for not filing it within that period

No outer limit in the text.

Worked example

The MCD passes a sealing order under Section 345A dated 01/09/2026; the owner receives it some days later.

Start date: 01/09/2026. Last date: 01/10/2026.

Thirty days run from the date of the order, so the last date is 01/10/2026 (a Thursday), whatever the date of receipt. A later appeal needs an application showing sufficient cause.

Common mistakes

Amendments and notes

Sections 347A to 347E were inserted by the Delhi Municipal Corporation (Amendment) Act, 1984 (Act 42 of 1984) with effect from 10/12/1985. The official consolidated text after the 2022 amendment unifying the Corporation was not opened; two reproductions agree on Section 347B(2). Whether delay can be condoned in an appeal under Section 343(2) was not settled in the sources checked, so no separate demolition entry is given. The Supreme Court's order of 10/01/2022 in In Re: Cognizance for Extension of Limitation (MA 21 of 2022 in SMW(C) 3 of 2020) excluded the period from 15/03/2020 to 28/02/2022 for limitation under general and special laws, including the outer limits within which a court or tribunal can condone delay; where limitation would have expired in that window, 90 days ran from 01/03/2022, or the longer balance period if any. It matters now only for orders communicated before 01/03/2022 that are still being contested on limitation.

Sources

Last verified 14/11/2026. Confidence: based on reproductions of the official text.

Disclaimer This page is published for general public legal education in compliance with the Bar Council of India Rules, Chapter II, Part VI, Rule 36, and is not an advertisement or solicitation. It does not create an advocate-client relationship. Limitation periods, pecuniary limits, addresses, sitting arrangements and procedures change; verify them for your own matter before acting.

Law stated as at 14/11/2026.