Appeal against orders or notices on building and planned development, including sealing of unauthorised construction (Section 345A), stoppage of work (Section 344), sanction or refusal of building plans (Section 336) and cancellation of sanction (Section 338) (Section 347B): what is the time limit?
- Provision
- Section 347B(2) and proviso
- Forum
- Appellate Tribunal, Municipal Corporation of Delhi (ATMCD)
- Period
- 30 days
- In the words of the entry
- Thirty days from the date of the order or notice appealed against
- The clock starts
- The date of the order or notice (not the date of its receipt)
Steps in order
- Further appeal against the ATMCD order: 30 days from the date of the Appellate Tribunal's order, to the Administrator (Section 347D(1) and (2), applying Section 347B(2)).
Why the law fixes this period
Building and sealing orders concern public safety and planned development, so challenges must be brought quickly before the position on the ground changes. The Tribunal may still hear a late appeal where the delay is explained.
How to calculate
- Count thirty days from the date the order or notice bears, excluding that day (Section 9, General Clauses Act, 1897); the section does not count from receipt (Section 347B(2)).
- The appeal must be accompanied by a copy of the order or notice and the prescribed fee (Section 347B(3)).
- A further appeal from the Tribunal's order lies to the Administrator, and Section 347B(2) applies to it, so it too must be filed within thirty days with the same power to admit late appeals (Section 347D(1) and (2)).
- A demolition order under Section 343(1) is not appealed under Section 347B; the appeal lies under Section 343(2) within the period specified in the demolition order itself, which is between five and fifteen days from delivery of the order (Section 343(1) and (2)).
- Whether Section 4 of the Limitation Act applies to a last day that falls on a holiday before the Tribunal was not verified; treat the date shown as the last day.
Condonation of delay
- Can delay be condoned?
- Yes
- Provision
- Proviso to Section 347B(2)
- Test
- sufficient cause for not filing it within that period
No outer limit in the text.
Worked example
The MCD passes a sealing order under Section 345A dated 01/09/2026; the owner receives it some days later.
Start date: 01/09/2026. Last date: 01/10/2026.
Thirty days run from the date of the order, so the last date is 01/10/2026 (a Thursday), whatever the date of receipt. A later appeal needs an application showing sufficient cause.
Common mistakes
- Counting from the date the order was received instead of the date of the order.
- Treating a demolition order under Section 343 as subject to the thirty days of Section 347B; its period is the one fixed in the order.
- Filing a civil suit against the order; Section 347E bars courts from entertaining suits and applications on matters within the Tribunal's jurisdiction.
Amendments and notes
Sections 347A to 347E were inserted by the Delhi Municipal Corporation (Amendment) Act, 1984 (Act 42 of 1984) with effect from 10/12/1985. The official consolidated text after the 2022 amendment unifying the Corporation was not opened; two reproductions agree on Section 347B(2). Whether delay can be condoned in an appeal under Section 343(2) was not settled in the sources checked, so no separate demolition entry is given. The Supreme Court's order of 10/01/2022 in In Re: Cognizance for Extension of Limitation (MA 21 of 2022 in SMW(C) 3 of 2020) excluded the period from 15/03/2020 to 28/02/2022 for limitation under general and special laws, including the outer limits within which a court or tribunal can condone delay; where limitation would have expired in that window, 90 days ran from 01/03/2022, or the longer balance period if any. It matters now only for orders communicated before 01/03/2022 that are still being contested on limitation.