Lokesh Bhardwaj Law Offices · Advocates and Legal Consultants, New Delhi · lokeshbhardwajlawoffices.com
Reference · Limitation
Limitation under the Real Estate (Regulation and Development) Act, 2016
This page sets out 3 proceedings under the Real Estate (Regulation and Development) Act, 2016: the provision, the period and the event that starts it, why the law fixes it, how to count it, whether delay can be condoned, a worked example and common mistakes.
Appeal to the Real Estate Appellate Tribunal against a direction, decision or order of the Authority or the adjudicating officer (Section 44): what is the time limit?
Provision
Section 44(2) and its proviso; proviso to Section 43(5) (pre-deposit by promoter)
Forum
Real Estate Appellate Tribunal of the State or Union territory
Period
60 days
In the words of the entry
60 days from the date a copy of the direction, order or decision is received by the appellant; the Tribunal may entertain it after 60 days on sufficient cause
The clock starts
The date on which the appellant receives a copy of the direction, order or decision
Why the law fixes this period
Homebuyer disputes need quick finality, so a fixed period runs from receipt of the order. A promoter must deposit part of the amount payable before the appeal is heard, so that appeals are not used to delay refunds.
How to calculate
Count 60 days from receipt of a copy of the order, excluding the day of receipt (Section 44(2); Section 9, General Clauses Act, 1897).
A promoter's appeal is not entertained without first depositing at least 30 per cent of the penalty (or a higher percentage fixed by the Tribunal), or the total amount payable to the allottee with interest and compensation, or both, before the appeal is heard (proviso to Section 43(5)).
The Tribunal is to endeavour to dispose of the appeal within 60 days of receipt (Section 44(5)).
Condonation of delay
Can delay be condoned?
Yes
Provision
Proviso to Section 44(2)
Test
sufficient cause
No cap is stated in the Act.
Worked example
An allottee receives a copy of the Authority's order refusing interest on 11/05/2026.
Start date: 11/05/2026. Last date: 10/07/2026.
Excluding 11/05/2026, 60 days end on 10/07/2026. A later appeal needs an application showing sufficient cause. Whether a Tribunal holiday on the last day moves the date depends on State rules and was not verified.
Common mistakes
Counting from the date of the order instead of receipt of its copy.
A promoter filing without the pre-deposit.
Assuming the Limitation Act's Section 5 is the source of condonation; the Act has its own proviso.
Amendments and notes
Text read from the Gazette copy of the Act on India Code (Act 16 of 2016). No central amendment to Sections 43 or 44 was found; the Jan Vishwas (Amendment of Provisions) Bill, 2026 reportedly proposes changing a penalty under the Act, and a Himachal Pradesh amendment Bill of 2025 was reported, neither verified as affecting appeal periods. State rules prescribe the form and fee. The Supreme Court's order of 10/01/2022 in Suo Motu Writ Petition (C) No. 3 of 2020 excluded 15/03/2020 to 28/02/2022 for all limitation, condonable outer limits and termination periods under general and special laws; where limitation would have expired in that window, at least 90 days from 01/03/2022 were allowed (to 29/05/2022).
Last verified 14/11/2026. Confidence: based on the official text.
Appeal to the High Court against a decision or order of the Real Estate Appellate Tribunal (Section 58): what is the time limit?
Provision
Section 58(1) and its proviso
Forum
High Court of the State or Union territory where the project is situated
Period
60 days
In the words of the entry
60 days from the date the Tribunal's decision or order is communicated to the appellant; the High Court may entertain it later on sufficient cause
The clock starts
The date of communication of the Appellate Tribunal's decision or order to the appellant
Why the law fixes this period
A second appeal is allowed only on the grounds in Section 100 CPC, that is, substantial questions of law. A fixed period from communication of the order gives finality.
How to calculate
Count 60 days from communication of the Tribunal's decision to the appellant, excluding that day (Section 58(1); Section 12(1), Limitation Act, 1963).
Exclude the time requisite for obtaining a certified copy if applied for (Section 12(2), Limitation Act, 1963, applied through Section 29(2)); this was not separately confirmed by a ruling under RERA.
The appeal lies only on the grounds in Section 100 CPC (Section 58(1)); no appeal lies from an order made with consent (Section 58(2)).
If the High Court is closed on the last day, the appeal may be filed when it reopens (Section 4, Limitation Act, 1963).
Condonation of delay
Can delay be condoned?
Yes
Provision
Proviso to Section 58(1)
Test
sufficient cause (appellant prevented by sufficient cause from preferring the appeal in time)
No cap is stated in the Act.
Worked example
The Tribunal's judgment is communicated to the promoter on 14/08/2026.
Start date: 14/08/2026. Last date: 13/10/2026.
Excluding 14/08/2026, 60 days end on 13/10/2026. A later appeal needs an application showing sufficient cause.
Common mistakes
Raising pure questions of fact in a Section 58 appeal.
Counting from the date of the judgment instead of its communication.
Filing in the High Court where the party resides rather than where the project is situated (Explanation to Section 58(1)).
Amendments and notes
No amendment to Section 58 was found. The Supreme Court's order of 10/01/2022 in Suo Motu Writ Petition (C) No. 3 of 2020 excluded 15/03/2020 to 28/02/2022 for all limitation, condonable outer limits and termination periods under general and special laws; where limitation would have expired in that window, at least 90 days from 01/03/2022 were allowed (to 29/05/2022).
Last verified 14/11/2026. Confidence: based on the official text.
Complaint to the Real Estate Regulatory Authority or the adjudicating officer (Section 31): what is the time limit?
Provision
Section 31(1); no Article of the Limitation Act applies on the view of the High Court of Chhattisgarh
Forum
Real Estate Regulatory Authority or its adjudicating officer (State or Union territory)
Period
No fixed period
In the words of the entry
No period of limitation is prescribed by the Act for a complaint. The High Court of Chhattisgarh has held that Article 137 of the Limitation Act does not apply because the Authority is not a court; some authorities instead apply a test of reasonable time
The clock starts
Not applicable (no prescribed period); delay may still be weighed by the Authority
Why the law fixes this period
Parliament gave allottees a regulatory remedy without fixing a time limit, and the Limitation Act applies to courts unless a special law extends it. The absence of a period protects allottees whose projects remain incomplete for years.
How to calculate
Section 31(1) allows any aggrieved person to complain of a contravention of the Act, rules or regulations, without a time limit (Section 31(1)).
Article 137 of the Limitation Act does not apply to a Section 31 complaint before the Authority or adjudicating officer (Nidhi Sao, High Court of Chhattisgarh, binding in that State).
A tribunal should not raise limitation for the first time on its own at the appellate stage when it was never raised or framed before the Authority (Nidhi Sao).
There is no Supreme Court ruling on the point as verified; other High Courts and some State authorities may take a reasonable-time approach, so long delay can still be argued against a complainant.
Condonation of delay
Can delay be condoned?
No
Provision
Not applicable
With no prescribed period there is nothing to condone; the question is whether the Authority treats the delay as unreasonable, which varies by State.
Worked example
The promoter's agreed possession date was 31/03/2025 and possession has not been given. The allottee has not yet complained.
Start date: 31/03/2025. Last date: no fixed last date.
No statutory last date applies. On the Chhattisgarh view the complaint is not barred by Article 137 even after three years. In a State whose Authority applies a reasonable-time test, a complaint filed long after the cause of action may be questioned, so the safe course in calculation is to treat no fixed date as available rather than to assume three years.
Common mistakes
Assuming a three-year bar under Article 137 applies everywhere.
Assuming the Chhattisgarh ruling binds Authorities in other States.
Confusing the complaint (no period) with the 60-day appeal under Section 44.
Rulings
Nidhi Sao v. Greenearth Infraventures Pvt. Ltd. (High Court of Chhattisgarh), 2026:CGHC:17484 (MA No. 173 of 2023, decided 16/04/2026): Article 137 of the Limitation Act does not apply to a complaint under Section 31(1) of RERA, because the Act prescribes no limitation for complaints and the Authority is not a court.
Amendments and notes
Haryana RERA has been reported (secondary sources only, not opened) to treat three years as a reasonable outer limit in at least one 2024 complaint, and the Haryana Appellate Tribunal has been reported (July 2026) to hold the Limitation Act inapplicable; these reports were not verified from the orders. The Supreme Court's COVID-period exclusion does not matter here because no period is prescribed.
Disclaimer
This page is published for general public legal education in compliance with the Bar Council of India Rules, Chapter II, Part VI, Rule 36, and is not an advertisement or solicitation. It does not create an advocate-client relationship. Limitation periods, pecuniary limits, addresses, sitting arrangements and procedures change; verify them for your own matter before acting.