Limitation under the Electricity Act, 2003

This page sets out 2 proceedings under the Electricity Act, 2003: the provision, the period and the event that starts it, why the law fixes it, how to count it, whether delay can be condoned, a worked example and common mistakes.

Appeal against an order of an adjudicating officer (except under Section 127) or of the Appropriate Commission (CERC or a State Commission) (Section 111): what is the time limit?

Provision
Section 111(2) and proviso
Forum
Appellate Tribunal for Electricity (APTEL)
Period
45 days
In the words of the entry
Forty-five days from the date on which a copy of the order is received by the aggrieved person
The clock starts
The date of receipt of a copy of the order of the adjudicating officer or the Commission

Why the law fixes this period

Tariff and regulatory orders affect the whole sector and consumers, so challenges must be brought quickly. The Tribunal keeps a discretion to admit late appeals on sufficient cause.

How to calculate

Condonation of delay

Can delay be condoned?
Yes
Provision
Proviso to Section 111(2)
Test
sufficient cause for not filing it within that period

No outer limit in the text, unlike the further appeal under Section 125.

Worked example

A copy of a State Commission's tariff order is received by a distribution licensee on 13/03/2026.

Start date: 13/03/2026. Last date: 27/04/2026.

Forty-five days after 13/03/2026 end on 27/04/2026 (a Monday).

Common mistakes

Amendments and notes

No amendment to Section 111(2) was found as at 14/11/2026. The Supreme Court's order of 10/01/2022 in In Re: Cognizance for Extension of Limitation (MA 21 of 2022 in SMW(C) 3 of 2020) excluded the period from 15/03/2020 to 28/02/2022 for limitation under general and special laws, including the outer limits within which a court or tribunal can condone delay; where limitation would have expired in that window, 90 days ran from 01/03/2022, or the longer balance period if any. It matters now only for orders communicated before 01/03/2022 that are still being contested on limitation.

Sources

Last verified 14/11/2026. Confidence: based on reproductions of the official text.

Appeal to the Supreme Court against a decision or order of APTEL on a ground in Section 100 CPC (Section 125): what is the time limit?

Provision
Section 125 and proviso
Forum
Supreme Court of India
Period
60 days
In the words of the entry
Sixty days from the date of communication of the decision or order of APTEL, extendable by a further period not exceeding sixty days on sufficient cause
The clock starts
The date on which the APTEL decision or order is communicated to the appellant (pronouncement made known with an opportunity to obtain a copy)

Why the law fixes this period

A second appeal to the Supreme Court on questions of law is the last step in sector disputes, so Parliament fixed a strict outer limit. The cap of 120 days gives certainty to regulators and utilities.

How to calculate

Condonation of delay

Can delay be condoned?
Yes
Provision
Proviso to Section 125
Test
appellant was prevented by sufficient cause
Outer limit
60 days
Section 5 excluded by
Proviso to Section 125 read with Section 29(2), Limitation Act, 1963; Chhattisgarh State Electricity Board v. CERC, (2010) 5 SCC 23 (Section 5 cannot be invoked beyond 120 days).

Beyond 120 days from communication the Supreme Court has held it cannot entertain the appeal.

Worked example

APTEL pronounces its judgment and the parties are informed and able to obtain a copy on 02/02/2026.

Start date: 02/02/2026. Last date: 03/04/2026.

Sixty days after 02/02/2026 end on 03/04/2026 (a Friday). On sufficient cause the Supreme Court can allow filing up to 02/06/2026, and not later.

Common mistakes

Rulings

Amendments and notes

No amendment to Section 125 was found as at 14/11/2026. The Supreme Court's order of 10/01/2022 in In Re: Cognizance for Extension of Limitation (MA 21 of 2022 in SMW(C) 3 of 2020) excluded the period from 15/03/2020 to 28/02/2022 for limitation under general and special laws, including the outer limits within which a court or tribunal can condone delay; where limitation would have expired in that window, 90 days ran from 01/03/2022, or the longer balance period if any. It matters now only for orders communicated before 01/03/2022 that are still being contested on limitation.

Sources

Last verified 14/11/2026. Confidence: based on the official text.

Disclaimer This page is published for general public legal education in compliance with the Bar Council of India Rules, Chapter II, Part VI, Rule 36, and is not an advertisement or solicitation. It does not create an advocate-client relationship. Limitation periods, pecuniary limits, addresses, sitting arrangements and procedures change; verify them for your own matter before acting.

Law stated as at 14/11/2026.