Interim Measures in Arbitration: Court, Tribunal and Emergency Arbitrator

An award months or years away is of little use if the money, goods or property in dispute disappear in the meantime. The Arbitration and Conciliation Act, 1996 gives two sources of interim protection, the court under Section 9 and the arbitral tribunal under Section 17, and institutional rules add a third, the emergency arbitrator.

In brief

Terms you will hear

Interim measure
A temporary order to protect the subject matter or the position of the parties until the dispute is decided, such as an injunction, an order to secure money, or the appointment of a receiver.
Section 9 petition
The application to the court for interim measures before, during or after the arbitration, up to enforcement of the award.
Section 17 application
The application to the arbitral tribunal for interim measures during the arbitral proceedings.
Emergency arbitrator
An arbitrator appointed under institutional rules, before the tribunal is formed, only to decide an urgent application for interim relief.
Securing the amount in dispute
An order requiring a party to deposit money, furnish a guarantee or refrain from dealing with assets, so that an award, if made, can be satisfied.
Court (Section 2(1)(e))
In a domestic arbitration, the principal civil court of original jurisdiction in a district, including a High Court on its ordinary original civil side; in an international commercial arbitration, the High Court.
Commercial Division and Commercial Court
The benches and courts that hear arbitration applications and appeals in commercial disputes of a specified value of Rs. 3 lakh or more, under Section 10 of the Commercial Courts Act, 2015.
Status quo
An order that the parties keep things as they are, often used to hold a position until the court or tribunal can hear both sides.

In detail

Interim measures from court under Section 9

When a party can apply

Section 9(1) allows a party to apply to the court for interim measures at three stages: before arbitral proceedings, during them, and at any time after the award is made but before it is enforced under Section 36. The measures the court may grant are:

The court has the same power to make these orders as it has in a proceeding before it.

Which court

The application goes to the court defined in Section 2(1)(e). In a domestic arbitration this is the principal civil court of original jurisdiction in the district, which includes the High Court where it has ordinary original civil jurisdiction. In an international commercial arbitration it is the High Court. Where the seat has been chosen, the courts of the seat have supervisory jurisdiction. Where the dispute is a commercial dispute of a specified value of Rs. 3 lakh or more, Section 10 of the Commercial Courts Act, 2015 places the application before the Commercial Division of the High Court, where the High Court has original jurisdiction, or otherwise before the Commercial Court. In Delhi, the High Court's original jurisdiction covers suits and matters of a value above Rs. 2 crore, and smaller matters go to the district Commercial Courts.

The 90-day rule and the tribunal's priority

If the court grants an interim measure before the arbitration begins, the arbitral proceedings must be commenced within 90 days from the date of the order, or within such further time as the court determines (Section 9(2)). Commencement means receipt by the respondent of the notice under Section 21, so the notice should be sent promptly. A party that obtains protection and then does nothing risks losing it.

Once the arbitral tribunal has been constituted, the court shall not entertain a Section 9 application unless it finds that circumstances exist which may not render the remedy under Section 17 efficacious (Section 9(3)). The rule reflects the 2015 policy that the tribunal, once formed, is the primary forum for interim relief. Circumstances that may justify going to court even then include urgency that the tribunal cannot meet in time, and relief against persons who are not parties to the arbitration, over whom the tribunal has no power.

What the court looks at

The court applies the familiar tests for interim relief: whether the applicant has a prima facie case, where the balance of convenience lies, and whether it will suffer irreparable harm without the order. It also asks whether the relief sought is truly interim and in aid of the arbitration, rather than the final relief claimed. An order to secure the amount in dispute is not granted as a matter of course on a money claim; the applicant should place material before the court showing a real risk that the other side will put its assets out of reach before an award. Full and frank disclosure is essential, especially where relief is sought without notice.

The documents

A Section 9 petition is supported by the arbitration agreement, the contract, the correspondence showing the dispute, the notice invoking arbitration or an undertaking to send it, and evidence of the threat to the subject matter. Court fee is payable under the court fee rules of the court concerned.

Appeal

An order granting or refusing to grant an interim measure under Section 9 is appealable under Section 37(1)(b). No second appeal lies (Section 37(3)). Where the Commercial Courts Act applies, the appeal is heard by the Commercial Appellate Division of the High Court or the Commercial Appellate Court and is filed within 60 days of the order (Section 13(1A) of that Act); otherwise the period in the Limitation Act, 1963 applies. The time limits are explained on the Office's page on limitation under the Arbitration Act.

Interim measures from the tribunal under Section 17

The powers

Section 17(1), as substituted in 2015, gives the arbitral tribunal power, during the arbitral proceedings, to grant on a party's application the same range of interim measures as a court can under Section 9: preservation, custody or sale of goods, securing the amount in dispute, detention, preservation or inspection of property, an interim injunction or receiver, and any other measure that appears just and convenient. The tribunal has the same power to make orders as a court in proceedings before it.

Since the 2019 amendment, the tribunal's power runs only during the arbitral proceedings; the earlier words allowing a tribunal to act after the award, until enforcement, were omitted. After the award, interim relief is sought from the court under Section 9.

Enforcement

An order of the tribunal under Section 17 is deemed to be an order of the court for all purposes and is enforceable under the Code of Civil Procedure, 1908 in the same manner as if it were an order of the court (Section 17(2)). Before the 2015 amendment, a party had to go to court for enforcement; now the order can be executed directly.

Appeal

An order of the tribunal granting or refusing an interim measure under Section 17 is appealable to the court under Section 37(2)(b). A tribunal order is subject to any order the court passes in that appeal.

Practical points

A Section 17 application is made by a written application in the arbitration, with an affidavit and documents, and the other side is heard unless the urgency justifies an order before it can be. Because the tribunal can act only against parties to the arbitration, relief against a bank, a guarantor who is not a party, or a third party holding assets may still need the court.

Emergency arbitration

What it is

Emergency arbitration allows a party to obtain urgent interim relief from a specially appointed arbitrator before the full tribunal is formed. The Arbitration and Conciliation Act, 1996 does not mention emergency arbitrators; the procedure exists where the parties have agreed to institutional rules that provide for it. The draft Arbitration and Conciliation (Amendment) Bill, 2024 proposed statutory recognition, but as verified on 16/11/2026 it had not been introduced in Parliament.

The DIAC Rules, 2023

Rule 14 of the Delhi International Arbitration Centre (Arbitration Proceedings) Rules, 2023 provides the procedure for arbitrations under those rules:

In Municipal Corporation of Delhi v. Himalyan Flora and Aromas Pvt. Ltd., decided by the High Court of Delhi on 08/10/2025 in an appeal under Section 37, the High Court held that an emergency arbitrator cannot extend the life of his own order beyond 90 days, since Rule 14.13 gives that power only to the tribunal, and set aside an order that had remained in force for about 11 months. The lesson is practical: once an emergency order is obtained, the tribunal must be constituted and asked to continue the relief before the 90 days end.

Status of the order

An emergency arbitrator's order in an arbitration seated in India, under rules the parties have chosen, is treated as an interim measure of the arbitral tribunal under Section 17: it is enforced under Section 17(2), and it is appealed under Section 37(2)(b), as the High Court of Delhi's decision of 08/10/2025 illustrates.

Choosing between an emergency arbitrator and the court

Emergency arbitration is quick and private, but its order binds only the parties, lasts only for a limited period and depends on the other side's compliance or on enforcement proceedings. A court order under Section 9 is backed by the court's own powers of enforcement, and the court is the forum where relief touching persons outside the arbitration is sought. The choice depends on what must be protected, against whom and how fast.

Interim relief in foreign-seated arbitration

Section 9 for a foreign seat

Part I of the Act applies where the seat of arbitration is in India (Section 2(2)). The proviso to Section 2(2), added in 2015, makes an exception: subject to an agreement to the contrary, Sections 9 and 27, clause (a) of Section 37(1) and Section 37(3) also apply to an international commercial arbitration even if the place of arbitration is outside India. A party to an arbitration seated in Singapore, London or elsewhere can therefore apply to an Indian court for interim measures against assets or conduct in India, unless the parties have excluded it. The words used in the proviso are those of the statute; after the 2015 amendment the appeal against a Section 9 order is in clause (b) of Section 37(1), and whether an appeal lies in a foreign-seated case should be checked on the current text and case law before relying on it.

When the parties have agreed otherwise

The proviso yields to an agreement to the contrary, so the arbitration clause and the institutional rules the parties chose are read for any exclusion of court relief before an application is made. Where they say nothing to exclude it, the Indian court's power under Section 9 is available.

Orders of foreign emergency arbitrators and tribunals

The Act contains no provision for directly enforcing in India an interim order made by an emergency arbitrator or a tribunal in an arbitration seated outside India. Part II enforces foreign awards, and an interim order is ordinarily not an award. A party that has obtained interim relief abroad and needs it to bite on assets in India usually applies afresh under Section 9 to the Indian court, placing the foreign order before the court as part of the material, and the Indian court decides the application on its own tests.

Assistance in taking evidence and reference to arbitration

Section 27, also applied to foreign-seated international commercial arbitrations by the proviso to Section 2(2), allows the court to assist in taking evidence. If a party sues in an Indian court in breach of an agreement to arbitrate abroad, the court refers the parties to arbitration under Section 45 unless it prima facie finds the agreement null and void, inoperative or incapable of being performed. The resulting award, when made, is enforced as a foreign award under Part II.

Common mistakes

Questions people ask

Can I get an injunction from court before starting arbitration?

Yes. Section 9 of the Arbitration and Conciliation Act, 1996 allows a party to apply to the court before arbitral proceedings begin, for measures such as preserving goods, securing the amount in dispute, an interim injunction or a receiver. If the court grants relief, Section 9(2) requires the arbitration to be commenced within 90 days of the order or such further time as the court allows. Commencement means the other side receiving the notice invoking arbitration under Section 21, so the notice should be ready to send as soon as the order is made.

Can I still go to court once the arbitral tribunal is formed?

Only in limited cases. Section 9(3) says that once the tribunal is constituted, the court shall not entertain a Section 9 application unless it finds that circumstances exist which may not make the remedy before the tribunal under Section 17 efficacious. Examples are urgency the tribunal cannot meet in time, or relief needed against a person who is not a party to the arbitration. Otherwise, interim relief during the arbitration is sought from the tribunal, whose orders are enforceable like the court's under Section 17(2).

Are interim orders of an arbitral tribunal enforceable?

Yes. Section 17(2), as substituted in 2015, provides that an order of the tribunal under Section 17 is deemed to be an order of the court for all purposes and is enforceable under the Code of Civil Procedure, 1908 in the same manner as an order of the court. A party aggrieved by the order may appeal to the court under Section 37(2)(b), and the tribunal's order is subject to any order passed in that appeal. Since 2019 the tribunal may grant interim measures only during the arbitral proceedings, not after the award.

Will the court freeze the other side's bank account in an arbitration?

It can, but not as a matter of course. Section 9 allows the court to secure the amount in dispute and to grant injunctions, which can include restraining a party from dealing with its accounts or assets. Courts generally expect the applicant to show a prima facie case and some real risk that the other side will put its assets beyond reach before an award, and they look at the balance of convenience and irreparable harm. Where the bank is not a party to the arbitration, an order affecting it is usually sought from the court rather than the tribunal.

What is emergency arbitration under the DIAC Rules?

Rule 14 of the Delhi International Arbitration Centre (Arbitration Proceedings) Rules, 2023 lets a party seek urgent interim measures before the tribunal is formed. DIAC appoints an emergency arbitrator within two days of the request, excluding non-business days. A hearing schedule is fixed within two business days, both sides are heard, and a reasoned order is to be made within 14 days of appointment. The order lasts 90 days from its date unless the tribunal modifies, substitutes, vacates or extends it. The emergency arbitrator does not sit on the tribunal unless all parties agree.

Can an emergency arbitrator's order last more than 90 days?

Only if the arbitral tribunal extends it. Rule 14.13 of the DIAC Rules, 2023 keeps the order operative for 90 days from the date it is passed unless the tribunal modifies, substitutes or vacates it, and gives only the tribunal power to extend it. On 08/10/2025 the High Court of Delhi, hearing an appeal under Section 37, set aside an emergency order that the emergency arbitrator had himself extended, because the order had lapsed after 90 days. The tribunal should therefore be constituted, and asked to continue the relief, well before the 90 days end.

Is a 90-day deadline attached to Section 9 relief?

Yes, where relief is granted before the arbitration starts. Under Section 9(2), the arbitral proceedings must be commenced within 90 days from the date of the order, or within such further time as the court determines. The arbitration commences when the respondent receives the notice invoking arbitration (Section 21). A party that does not send the notice in time risks the order being vacated. If more time is genuinely needed, for example for a mandatory pre-arbitration step, the party should ask the court to extend the period before it expires.

Can an Indian court give interim relief if the arbitration is seated in Singapore or London?

Yes, unless the parties have agreed otherwise. The proviso to Section 2(2) of the Arbitration Act, added in 2015, applies Section 9 to international commercial arbitrations even when the place of arbitration is outside India. A party can therefore seek an injunction or an order securing assets in India in aid of a foreign-seated arbitration. The application goes to the High Court. The court will check whether the agreement or the chosen rules exclude such relief, and will apply its own tests for interim relief.

Can I enforce a foreign emergency arbitrator's order in India?

Not directly. The Act has no provision for enforcing in India an interim order made by an emergency arbitrator or tribunal in an arbitration seated abroad, and Part II of the Act deals with foreign awards, not interim orders. The usual course is a fresh application to the Indian court under Section 9, which is available for foreign-seated international commercial arbitrations unless excluded, placing the foreign order before the court as part of the material. The Indian court then decides on its own tests whether to grant relief.

How long do I have to appeal a Section 9 order?

It depends on whether the Commercial Courts Act, 2015 applies. In a commercial dispute of a specified value of Rs. 3 lakh or more, the appeal under Section 37(1)(b) of the Arbitration Act goes to the Commercial Appellate Division of the High Court or the Commercial Appellate Court and must be filed within 60 days of the order under Section 13(1A) of that Act. In other cases the periods in the Limitation Act, 1963 apply. No second appeal lies, but the right to approach the Supreme Court is preserved.

These answers are educational summaries; they are not legal advice on any individual matter.

Engagement

A serious question deserves a read brief.

Conferences are by appointment at G-46, Basement, Greater Kailash III, New Delhi. The principal reads the correspondence.

Disclaimer This page describes areas in which the Office accepts work; it is informational, published in compliance with the Bar Council of India Rules, Chapter II, Part VI, Rule 36, and is not an advertisement or solicitation. Nothing here is legal advice, and no lawyer-client relationship arises from reading it.

This page gives general information about the work of Lokesh Bhardwaj Law Offices, as permitted under the Bar Council of India Rules. It is not legal advice, and it does not create an advocate-client relationship. LBLO acts in a matter only on an engagement agreed in writing.

Last reviewed: 16/11/2026. Lokesh Bhardwaj Law Offices.

Law stated as at 16/11/2026.

WhatsApp