Arbitral Proceedings, the DIAC and Costs: From the Statement of Claim to the Award

Once the arbitral tribunal is in place, the dispute is decided in proceedings that the parties largely shape themselves, inside a framework that the Arbitration and Conciliation Act, 1996 fixes.

In brief

Terms you will hear

Statement of claim
the claimant's written case: the facts, the points in issue and the relief sought, with the documents relied on (Section 23(1) and (2)).
Counter-claim and set-off
a claim by the respondent against the claimant, or an amount it says should be deducted. It is decided in the same arbitration if it falls within the arbitration agreement (Section 23(2A)).
Completion of pleadings
the date on which the statements of claim and defence are complete. The twelve months for the award run from this date (Sections 23(4) and 29A(1)).
Mandate
the arbitrator's authority to decide the dispute. It ends with the final award, a termination order, or the expiry of the time for the award unless the court extends it.
Fast track procedure
a written procedure, usually without oral hearings, in which the award must be made within six months of the tribunal entering on the reference (Section 29B).
Emergency arbitrator
an arbitrator appointed under institutional rules to grant urgent interim relief before the tribunal is formed (Rule 14, DIAC Rules, 2023).
Costs
the reasonable fees and expenses of the arbitrators, courts and witnesses, legal fees and expenses, the institution's administrative fees and other expenses of the proceedings and the award (Explanation to Section 31A(1)).
Pendente lite and post-award interest
interest for the period before the award, which the tribunal may include at a reasonable rate unless the parties agreed otherwise (Section 31(7)(a)), and interest from the award until payment (Section 31(7)(b)).

In detail

This page follows an arbitration from the constitution of the tribunal to the award. The earlier steps are on the page on starting an arbitration, urgent relief on the page on interim measures, and what follows the award on the page on challenges and appeals. The parties are free to agree on the procedure, the place and the language; failing agreement, the tribunal decides (Sections 19, 20 and 22). In institutional arbitration, the institution's rules supply most of the procedure.

Claims, counter-claims and evidence

1. The statement of claim and the defence

Within the time agreed or fixed by the tribunal, the claimant states the facts, the points at issue and the relief sought, and the respondent states its defence, each with the documents it relies on (Section 23(1) and (2)). Since 2015 the respondent may also submit a counter-claim or plead a set-off, decided in the same arbitration if it falls within the arbitration agreement (Section 23(2A)). Either party may amend its case unless the tribunal considers the amendment inappropriate because of delay (Section 23(3)).

2. The six-month period for pleadings

The statement of claim and defence must be completed within six months from the date on which the arbitrator, or all the arbitrators, received written notice of their appointment (Section 23(4), inserted in 2019). The date of completion matters because it starts the twelve-month period for the award under Section 29A.

3. When a party does not take part

Unless the parties agreed otherwise, and where no sufficient cause is shown (Section 25):

A respondent who stays away therefore does not stop the arbitration. The award that follows can be enforced like a decree unless it is set aside.

4. Hearings and evidence

The tribunal decides whether to hold oral hearings or proceed on documents, but must hold an oral hearing at an appropriate stage if a party asks, unless the parties agreed otherwise (Section 24(1)). Hearings are to be held day to day as far as possible, and a party seeking an adjournment without sufficient cause may be made to pay costs. Everything one party supplies to the tribunal, and any expert report or document the tribunal may rely on, must be communicated to the other side (Section 24(3)).

The formal rules of proof of a civil suit do not bind the tribunal, but it must decide on evidence both parties have seen. It may appoint its own expert, who can then be questioned at a hearing (Section 26). Where a witness or document has to be compelled, the tribunal, or a party with its approval, may apply to the court for assistance in taking evidence (Section 27).

5. Interim awards, settlement and confidentiality

The tribunal may make an interim award on any matter on which it could make a final award (Section 31(6)). A settlement may be recorded as an award on agreed terms, with the same status as any other award (Section 30). The proceedings are confidential, except the award where disclosure is needed to implement or enforce it (Section 42A).

6. Common mistakes

Time limits for the award (Section 29A)

1. Twelve months, plus six by consent

Section 29A was inserted in 2015 and recast in 2019. In matters other than international commercial arbitration, the award must be made within twelve months from the date of completion of pleadings under Section 23(4) (Section 29A(1)). In an international commercial arbitration the award is to be made as expeditiously as possible, with an endeavour to finish within twelve months of the completion of pleadings (proviso to Section 29A(1)). The parties may by consent extend the period by up to six months (Section 29A(3)). If the award is made within six months of the tribunal entering on the reference, the tribunal is entitled to such additional fees as the parties agree (Section 29A(2)).

2. What happens when time runs out

If the award is not made within the period, or the extended period, the mandate of the arbitrators terminates unless the court has extended the period, either before or after its expiry (Section 29A(4)). While an application for extension is pending, the mandate continues until the application is decided (second proviso to Section 29A(4)).

The Supreme Court has held that an application for extension under Section 29A(4) read with Section 29A(5) is maintainable even after the twelve-month or the extended eighteen-month period has expired, and that termination under the section is not absolute; extension is granted only for sufficient cause and on terms, and not mechanically (Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., 2024 INSC 686, decided 12/09/2024).

3. The court's powers on an extension application

4. Fast track arbitration

The parties may agree in writing, before or at the appointment of the tribunal, to the fast track procedure: the dispute is decided on written pleadings, documents and submissions, with an oral hearing only if all parties ask or the tribunal considers it necessary, and the award is due within six months of the tribunal entering on the reference, after which Section 29A(3) to (9) apply (Section 29B).

In Jammu and Kashmir and Ladakh, the 2020 adaptation orders keep the earlier rule that the twelve months run from the tribunal entering on the reference. A worked example is on the Office's limitation page for the Arbitration Act.

Institutional arbitration at the DIAC

1. What the DIAC is

The Delhi International Arbitration Centre, formerly the Delhi High Court Arbitration Centre, was established by the High Court of Delhi and functions in the High Court campus at Shershah Road, New Delhi. It is overseen by an Arbitration Committee, and its day-to-day administration is run by a Coordinator and Additional Coordinators. It is not created by an Act of its own: its rules come into force on approval by the Chief Justice of the High Court of Delhi (Rule 1.4, DIAC (Arbitration Proceedings) Rules, 2023). It should not be confused with the India International Arbitration Centre, a separate centre established by an Act of Parliament.

Three sets of rules apply: the DIAC (Arbitration Proceedings) Rules, 2023, in the consolidated text the Centre published in April 2026; the DIAC (Internal Management) Rules, 2012; and the DIAC (Administrative Cost and Arbitrators' Fees) Rules, 2018. They apply where the parties agreed to refer disputes to the DIAC, where a court directs arbitration under them, or where a reference is made to the DIAC in accordance with law, and the Act prevails over any conflicting rule (Rules 1.2 and 1.3).

2. The request and the response

A party starts by filing a written request for arbitration with the DIAC, even where a court has referred the dispute there (Rule 4.1). It includes the arbitration clause and the contract; where the clause does not name the DIAC, a memorandum signed by both parties agreeing to arbitrate there; a short statement of the claims; for a sole arbitrator, five names from the DIAC panel, or for three arbitrators the party's nominee, who must not be ineligible under Section 12(5) of the Act; and proof of service and of payment of the administrative charges. An incomplete request is not treated as valid (Rule 4.2). The response is due within thirty days of receipt, failing which the other party is presumed to have consented to arbitration under the rules (Rule 5.1).

3. The tribunal

Unless the parties agreed on three arbitrators, there is one (Rules 8.1 and 8.2). A sole arbitrator is appointed from a name common to both lists or, failing that, by the Chairperson or a Sub-Committee; for three, the party-appointed arbitrators choose the presiding arbitrator within 21 days, failing which the Chairperson or Sub-Committee appoints within a further 21 days (Rules 8.3 to 8.6). A challenge to an arbitrator is made to the DIAC within 14 days of the appointment or of learning the grounds and is decided within 60 days, and the time for the award stands extended while it is pending (Rule 10).

4. Emergency arbitration and fast track

An emergency arbitrator is appointed within two days of the application, excluding non-business days, must hear both sides and must complete the process within fourteen days; the order remains operative for ninety days unless the tribunal modifies or vacates it, and the tribunal may extend it (Rule 14). Under the fast track procedure the parties undertake in writing to dispense with oral evidence, and the award is due within six months of the tribunal entering on the reference (Rules 12 and 13).

5. Pleadings, hearings and the award

The tribunal fixes the pleading timetable at the first procedural meeting, and a party that misses it may have its claim terminated or its defence or counter-claim foreclosed (Rules 16, 17 and 21.2). The language is English and the seat is New Delhi unless the parties expressly agree otherwise (Rules 22.1 and 23.1). Hearings may be in person or by video conference (Rule 26.1). The award is due within eighteen months from the completion of pleadings, including the six-month extension by consent under Section 29A(3), or such period as the court extends; at least 45 days before that, the tribunal submits its draft award for scrutiny by a committee that may suggest modifications without interfering with the decision on the merits (Rule 31.1).

Costs

1. The regime under Section 31A

The costs of an arbitration are fixed by the tribunal in accordance with Section 31A (Section 31(8)). In an arbitration, or in a court proceeding under the Act, the tribunal or the court has the discretion, notwithstanding the Code of Civil Procedure, to decide whether costs are payable by one party to another, the amount, and when they are to be paid (Section 31A(1)). If it decides to award costs, the general rule is that the unsuccessful party pays the costs of the successful party, but a different order may be made for reasons recorded in writing (Section 31A(2)).

The tribunal or court considers all the circumstances, including the conduct of the parties, partial success, a frivolous counter-claim that caused delay, and a reasonable settlement offer refused by the other side (Section 31A(3)). It may award a proportion or a stated amount of a party's costs, costs of particular steps, pre-proceeding costs and interest on costs (Section 31A(4)). An agreement that one party will pay the whole or part of the costs in any event is valid only if made after the dispute arose (Section 31A(5)), so such a clause in the original contract does not bind on that point.

2. Deposits and the arbitrators' fees

The tribunal may fix a deposit, separately for the claim and the counter-claim, payable in equal shares; if neither side pays a share, the tribunal may suspend or terminate the proceedings on that claim (Section 38). At the DIAC the Centre fixes the deposits under its fee rules, and a claim or counter-claim may be terminated if the deposit is not paid within thirty days of falling due, without prejudice to raising it again in other proceedings (Rules 33.1 and 33.5). In ad hoc arbitrations the High Court may frame rules for arbitrators' fees, taking into consideration the Fourth Schedule, except in international commercial arbitrations and where an institution's rules govern fees (Section 11(14)). The tribunal has a lien on the award for unpaid costs, subject to the court's power to order delivery on payment into court (Section 39).

3. Interest

Unless the parties agreed otherwise, the tribunal may award interest at a reasonable rate from the date the cause of action arose to the date of the award (Section 31(7)(a)). Unless the award otherwise directs, the sum awarded carries interest at two per cent above the current rate of interest, as defined in the Interest Act, 1978, from the award to payment (Section 31(7)(b)). A Constitution Bench has held that the court hearing a challenge may in some circumstances modify post-award interest (Gayatri Balasamy v. ISG Novasoft Technologies Ltd., 2025 INSC 605; see challenges to awards). LBLO keeps a running record of costs from the first procedural meeting so that a claim under Section 31A can be supported when the award is made.

Questions people ask

How long does an arbitration take in India?

The Act sets outer limits rather than a fixed length. Pleadings are to be completed within six months of the arbitrators receiving notice of their appointment (Section 23(4)), and in a domestic arbitration the award is due within twelve months of the completion of pleadings, extendable by six months with the consent of both parties (Section 29A). Beyond that, only the court can extend the time, for sufficient cause. A fast track arbitration must end in an award within six months of the tribunal entering on the reference (Section 29B). Under the DIAC Rules the award is due within eighteen months of the completion of pleadings, including the consent extension, unless the court extends it.

What happens if the arbitrator does not give the award within twelve months?

If the twelve months, and any six-month extension agreed by the parties, pass without an award, the arbitrator's mandate terminates unless the court extends the period (Section 29A(4)). Any party may apply to the court for an extension. The court grants it only for sufficient cause and on terms; it may reduce the arbitrator's fees by up to five per cent for each month of delay caused by the tribunal, may substitute the arbitrator, and may impose costs. While the application is pending, the mandate continues. The Supreme Court has held that the application can be made even after the period has expired.

Can the time for the award be extended after it has expired?

Yes. Section 29A(4) allows the court to extend the period "either prior to or after the expiry" of the time fixed. In Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., 2024 INSC 686, decided on 12/09/2024, the Supreme Court held that an application for extension under Section 29A(4) read with Section 29A(5) is maintainable even after the twelve months, or the extended period of six more months, have expired. The court will still examine whether there is sufficient cause and may impose terms, so a party should not treat the deadline lightly.

Can the respondent file a counter-claim in arbitration?

Yes. Since the 2015 amendment, Section 23(2A) allows the respondent to submit a counter-claim or plead a set-off, which the tribunal must decide if it falls within the scope of the arbitration agreement. Under the DIAC Rules, the counter-claim is filed with the statement of defence, within the time the tribunal fixes at the first procedural meeting, and a separate deposit towards costs may be fixed for it. A counter-claim outside the arbitration agreement cannot be decided in that arbitration.

Is an arbitrator bound by the Code of Civil Procedure and the law of evidence?

No. Section 19(1) says the arbitral tribunal is not bound by the Code of Civil Procedure, 1908 or the law of evidence, and Section 19(4) lets the tribunal decide the admissibility, relevance, materiality and weight of evidence. The tribunal must still treat the parties equally and give each a full opportunity to present its case (Section 18), and every document or expert report it relies on must be shared with both parties (Section 24(3)). An award based on material a party never saw is open to challenge.

What happens if the other side does not take part in the arbitration?

The arbitration goes on. If the respondent does not file its defence without sufficient cause, the tribunal continues the proceedings; the failure is not treated as an admission, but the tribunal may treat the right to file a defence as forfeited (Section 25(b)). If a party does not appear at a hearing or produce documents, the tribunal may make the award on the evidence before it (Section 25(c)). The claimant still has to prove its claim, and should keep proof that every notice was served.

What is the DIAC and how is an arbitration started there?

The Delhi International Arbitration Centre is the arbitration centre established by the High Court of Delhi in the High Court campus. An arbitration starts with a written request for arbitration filed with the DIAC under Rule 4 of its 2023 Rules, with the arbitration clause, the contract, a statement of the claims, suggested arbitrators from the DIAC panel, proof of service on the other side and proof of payment of the administrative charges. If the contract does not name the DIAC, both parties must sign a memorandum agreeing to arbitrate there. The other side has thirty days to respond.

Is the seat of a DIAC arbitration always New Delhi?

Not always, but it is the default. Rule 23.1 of the DIAC (Arbitration Proceedings) Rules, 2023 provides that unless the parties expressly agree otherwise, the seat is New Delhi. Hearings and meetings may be held at any venue or by video conference the tribunal considers appropriate in consultation with the parties, without changing the seat. The seat matters because it decides which court hears applications such as a challenge to the award.

Who pays the costs of the arbitration?

The tribunal decides. Under Section 31A, if it awards costs, the general rule is that the unsuccessful party pays the costs of the successful party, but it may make a different order for recorded reasons, looking at the parties' conduct, partial success, frivolous counter-claims and refused settlement offers. Costs include the arbitrators' fees and expenses, legal fees, the institution's charges and other expenses. A contract clause making one party pay all costs in any event is valid only if agreed after the dispute arose (Section 31A(5)).

Can an arbitrator refuse to release the award until fees are paid?

The tribunal has a lien on the award for unpaid costs of the arbitration (Section 39(1)). If it refuses to deliver the award except on payment, a party may apply to the court, which can order the tribunal to deliver the award once the party pays the amount demanded into court, and then decide what the tribunal should reasonably receive and refund the balance (Section 39(2)). This application is not available where the fees were fixed by written agreement between that party and the tribunal (Section 39(3)).

Are arbitration proceedings confidential?

Yes. Section 42A, inserted in 2019, requires the arbitrator, the arbitral institution and the parties to keep all arbitral proceedings confidential, except the award where disclosure is necessary to implement or enforce it. The DIAC Rules add that the parties, the Centre and the tribunal must treat all matters relating to the proceedings as confidential, subject to listed exceptions such as court proceedings to enforce or challenge the award (Rule 35). The DIAC may publish an award unless a party asks in writing before publication that it be kept confidential (Rule 31.3).

These answers are educational summaries; they are not legal advice on any individual matter.

Engagement

A serious question deserves a read brief.

Conferences are by appointment at G-46, Basement, Greater Kailash III, New Delhi. The principal reads the correspondence.

Disclaimer This page describes areas in which the Office accepts work; it is informational, published in compliance with the Bar Council of India Rules, Chapter II, Part VI, Rule 36, and is not an advertisement or solicitation. Nothing here is legal advice, and no lawyer-client relationship arises from reading it.

This page gives general information about the work of Lokesh Bhardwaj Law Offices, as permitted under the Bar Council of India Rules. It is not legal advice, and it does not create an advocate-client relationship. LBLO acts in a matter only on an engagement agreed in writing.

Last reviewed: 16/11/2026. Lokesh Bhardwaj Law Offices.

Law stated as at 16/11/2026.

WhatsApp